CURRENT STATE OF HUDSON RIVER PROJECT
According to the National
Resources Defense Council (NRDC), the environmentalists scored big in August
2002 when Christie Todd Whitman, head of the EPA, announced the Record of
Decision (ROD). In a joint state and GE-funded effort, the EPA would remove
approximately 2.65 million cubic yards of PCB-contaminated sediment from a 40-mile
stretch of the Upper Hudson. GE would be
responsible for most of the bill, but the state would contribute since they
issued the permit to allow waste disposal in the Hudson
Falls and Fort Edward
sites. The amount of PCBs removed during this project would be equivalent to
about 65 percent of the PCBs present in this stretch of the river. The EPA
expects to leave only one part per million of PCBs in the river after the
project is completed. The ROD included two phases for the project, the first
being a smaller dredge period in which the methods would be monitored to make
sure regulations are being met. During this time the EPA expects to dredge
200,000 to 300,000 cubic yards of sediment. Phase II would take place over a
longer time period – about five years according to the EPA – and would dredge
the remainder of the 2.65 million cubic yards of sediment. The two-phase method
was created to alleviate skepticism among local residents, as many felt the EPA
was undertaking a project that it could not actually complete (EPA 2002).
The
ROD also expressed a desire to develop and maintain a community involvement
plan during both phases of the project. According to Bonnie Bellow of the EPA,
“We are committed to an
open public process that will give affected communities and interested
organizations and individuals a chance to really provide input on the critical
issues related to this clean up plan. Our goal is to develop a community
involvement program that will encourage real dialogue, and I'm talking about
real dialogue” (EPA 2002, 15)
Despite EPA’s progress on the Hudson project, completion
seems to be a far-off objective at this point. The Remedial Design/Remedial
Action phase of the clean-up has now taken 5 years, and many stakeholders are
growing anxious for dredging to begin. In the summer of 2006, EPA
announced that dredging would be delayed until the 2008 dredging season.
According to U.S.
Regional Administrator Alan J. Steinberg,
"The Environmental Protection Agency [is] now
facing several obstacles beyond our control that make it unrealistic to begin
dredging during the 2007 dredging season. We have independently verified the
accuracy of the projected construction scheduled provided by GE and, after
careful review, must agree that its timeline for the delivery of key pieces of
equipment needed for the sediment dewatering and the installation of power
lines on the dewatering site is accurate. The review has led us to conclude
that [moving] the start of dredging into the 2008 dredging season is
unavoidable. We remain very hopeful that GE will begin the site preparation
work in the fall of this year, and we will continue the progress we have made
toward a cleaner Hudson for local communities and everyone who cherishes the
river" (Sediment.org Bulletin Board)
|

A crew collecting sediment samples from the
Hudson. Such samples are analyzed to determine the extent of the
pollution and inform potential remediation plans. Photo from http://www.hudsondredging.com. |