Wind Energy

Wind Energy - Visual Impacts and Public Perceptions

Case Studies: Controversial Wind Farms

 

All of the below wind projects have been identified as contentious on the grounds of aesthetic impact. Our definition of aesthetic impact includes issues regarding the perceived loss of property values, the loss of recreational opportunities, wildlife impacts in protected areas that are enjoyed by tourists and local residents, and in some cases sound pollution. The information is based on the current status of construction (August 2008). The table below includes an assessment of the level of controversy surrounding each project. The case studies are coded as:

  • Little opposition - The wind farm was opposed by a few individuals using traditional avenues of engagement, predominantly based in print media (letters to the editor, opinion editorials and press interviews), public comments submitted in response to an environmental impact review and participation in public hearings.
  • Moderately contentious - The wind farm was opposed by many individuals, who may have organized as a grassroots coalition against the project. Those opposing the project have engaged in a variety of pressure techniques including letters to the editors, public comments submitted in response to an environmental impact statement, the development of websites that help network and organize opposition, and the issuance of counter simulations and data regarding the project.
  • Highly contentious - The wind farm was opposed by many individuals often represented by several organized groups. These groups used diverse means to try to prevent the project, including lawsuits, the formation of political parties, the creation of alternative impact statements and visualizations, and the participation at public hearings and the submission of public comments.

Wind Controversy Case Studies Map

Wind Farm

Location

Scale

Developer

Level of Controversy

Status

Elk River

Butler County, KS

100 Turbines 150 MW

Iberdrola

Moderately contentious

Completed

Forward Wind Energy Center

Fond Du Lac and Dodge Counties, WI

86 Turbines
129 MW

Invenergy

Highly contentious

Completed

Horse Hollow

Taylor and Nolan Counties, TX

421 Turbines 735 MW

FPL Energy

Moderately contentious

Completed

Wild Horse

Kittitas County, WA

127 Turbines 230 MW

Horizon / Puget Sound Energy

Little opposition

Completed

Cohocton Wind

Steuben County, NY

35 Turbines
87 MW

First Wind

Highly contentious

Completed

Highland Wind

Highland County, VA

20 Turbines
40 MW

Highland New Wind Development

Highly contentious

Approved and under construction

Valley County Wind Energy Project

Valley County, MT

~6 turbines
10 MW

GreenHunter

Moderately contentious

Scaled back from 500 MW project to 10 MW test facility and completed

Redington / Black Nubble Wind

Franklin County, ME

18 Turbines
54 MW

Maine Mountain Power

Highly contentious

Delayed

Jordanville Wind Farm

Jordanville, NY

49 Turbines
98 MW

Community Energy / Iberdrola

Highly contentious

Scaled back from 65 turbines and delayed

Cascade Wind

Wasco County, OR

40 Turbines
60 MW

First Wind

Highly contentious

Cancelled

 

Last updated January 2012.

Creative Commons License
This work by Roopali Phadke is licensed under a Creative Commons Attribution-Noncommercial-No Derivative Works 3.0 United States License.